ACE Arte Payment Plan 20X5: 10% on Booking, 10% Within 30 Days, Then Four 20% Blocks
ACE Arte, Sector 150 Noida: the published facts
- ACE Arte is a residential project in Sector 150, Noida by ACE Group, registered with UP-RERA as UPRERAPRJ528653/07/2026.
- ACE Arte payment plan is 20X5: 10% on booking, 10% within 30 days, 20% at ground-floor slab, 20% at 10th-floor slab, 20% on structure completion and 20% on offer of possession.
- ACE Arte pre-launch BSP is ₹16,995/sq.ft* per ACE's price list W.E.F. 21-08-2026, against a launch rate of ₹21,995/sq.ft*; GST is extra.
- ACE Arte EOI is ₹10 lakh, ₹15 lakh or ₹20 lakh by configuration, refundable in full if no unit is allotted, per the price list W.E.F. 21-08-2026.
- ACE Arte sizes are 1,927, 2,614 and 4,370 sq.ft* for the 3 BHK, 4 BHK and 4 BHK + servant, printed as tentative on the price list W.E.F. 21-08-2026.
Facts as ACE published them, reviewed 6 September 2026
Quick answer
ACE Arte's 20X5 plan is five blocks of 20% of the base sale price. Read as money leaving your account, it lands in three parts. 20% on the calendar, being 10% on booking and 10% within 30 days. Then 60% against three site events you can go and look at, being 20% after ground-floor slab casting, 20% after 10th-floor slab casting and 20% on completion of the super structure. Then the last 20% plus other charges on a letter, the offer of possession.
Source for every line name and share on this page: the price list W.E.F. 21-08-2026, which the desk read on 3 September 2026.
Six printed lines take an ACE Arte booking from 10% to the keys. What the ladder does not tell you is which line you should be standing on site to confirm, which one needs a date pinned in writing on day one, and which one opens a bill the base rate was never carrying. This page reads “20X5” as a sequence of buyer decisions rather than a table of percentages. ACE Arte is the UP-RERA registered name for ACE Parkway 2.0 in Sector 150 on the Noida Expressway. Our sales desk is an authorised UP-RERA registered channel partner, agent UPRERAAGT000309/01/2026, and is not the developer.
What each line of 20X5 asks you to do
Five blocks of 20% of the base sale price, and the first of those blocks arrives as two separate payments of 10%. That is where the name comes from. Below is the printed ladder with the buyer's job set against each line, which is the part the price list leaves to you:
- 10%On booking
Have the collection account details and the cheque-favour wording in front of you before this one moves. - 10%Within 30 days
A date, not a site condition. Get the exact due date in writing on the day you book, because nothing at the site will remind you it is coming. - 20%After slab casting of the ground floor
Ask which tower the demand names, then go and see whether that slab is poured before you release. - 20%After slab casting of the 10th floor
The same check, ten floors up. If the demand does not name a tower, ask for it in writing. - 20%On completion of super structure
Topped out, with the finishing work still to come. Confirm the stage before you transfer, not afterwards. - 20% + other chargesOn offer of possession
Printed with “plus other charges”, so a second bill opens with it. Have the charge heads itemised in writing long before this letter arrives.
Line names and percentages are as printed on the price list W.E.F. 21-08-2026, read on 3 September 2026. The note beside each line is our reading of what the buyer has to do, not wording lifted from the document. ACE may revise the plan, and the schedule that binds you is the one recorded in your Agreement for Sale. Nothing on this page is an offer.
The lines to confirm on site before you release them
Lines 3, 4 and 5, and the confirmation costs you an afternoon. Concrete is not paperwork. A ground floor slab in a named tower has been poured or it has not, and the same holds for the 10th-floor slab and for a frame that has topped out. So the habit worth building is a small one: when a demand letter lands against any of those lines, ask which tower and which stage it refers to, then go and see it before you transfer. The outer frame those three checks sit inside comes from the register, which separately records construction proposed to start 15 August 2026 and completion declared 15 February 2031, as the UP-RERA tracker read the entry on 29 July 2026. Verify the live entry yourself at up-rera.in.
The other three lines give you nothing to inspect. Booking and the 30-day payment answer to a calendar, and the “offer of possession” is a legal act by the developer that usually follows the occupancy paperwork, so it reaches you as a letter rather than as anything visible from the road. Those three you cover with documents instead, which is what the rest of this page is about.
Inside your first 30 days
Twenty per cent of the base sale price is committed before line 3 can physically exist. That is the stretch of the plan with the least for you to verify and the most riding on getting the instruction right, because it answers to a calendar, and a calendar does not wait for a site visit.
So two things are worth fixing in writing inside those 30 days rather than after them. First, the account the money must reach, together with the cheque-favour wording and the rule that no payment ever goes to an individual, all of which sit on our guide to the ACE Arte EOI process and its refund rule. Second, the exact calendar date the second 10% falls due, written against your unit, because nothing at the site will announce it. Why the account you pay into matters as much as the amount is set out in our note on what a RERA collection account actually protects.
What the last line does not cover
Everything the base rate was never carrying. Line 6 is printed as “20% plus other charges”, and the price list names PLC, GST and other charges as extra without printing a rupee figure against any of them, while stamp duty and statutory charges are borne by the buyer. Read forward, that makes the possession demand the first piece of paper in the whole sequence where those heads reach you as amounts you have to fund.
The way to keep that from being a surprise is to move the question to the front of the deal instead of the end. At booking stage, ask the desk to set the charge heads out itemised in writing against your configuration, so that when the letter does arrive you are reconciling a list you already hold rather than reading one for the first time. The rate those heads sit on top of is on our ACE Arte price list, row by row, read from the same document as this plan, and what that rate buys inside the walls is on our room-by-room ACE Arte specification.
How 20X5 changes what you compare
Treat the label carefully. A plan can be described as “construction-linked” while its opening payments still answer to a calendar, and 20X5 has exactly that shape: it starts on dates (booking plus 30 days), runs on concrete through the frame, and finishes on a legal act. So when you set this plan beside another project's, the figure to put side by side is not the headline split but how much of the base sale price leaves your account before anyone can show you a poured slab. Under 20X5 that figure is 20%. What a slab casting actually is, and why it is the trigger worth watching, is set out in our note on slab casting and construction-linked plans.
ACE Arte booking amount
The ACE Arte booking amount has two parts on the price list W.E.F. 21-08-2026. First, the EOI that enters you into the queue: ₹10,00,000 for the 1,927 sq.ft* 3 BHK, ₹15,00,000 for the 2,614 sq.ft* 4 BHK, or ₹20,00,000 for the 4,370 sq.ft* 4 BHK + S, refunded in full without any deduction if a unit is not allotted. Second, once a unit is allotted, the opening line of the 20X5 plan itself: 10% of the base sale price on booking, followed by a further 10% within 30 days. The EOI adjusts into that opening 10% rather than standing beside it, as set out on our ACE Arte EOI process page.
The ACE Arte 20X5 payment scheme, line by line
The ACE Arte 20X5 payment scheme is five blocks of 20% of the base sale price: the first block split into 10% on booking and 10% within 30 days, then 20% each after ground-floor slab casting, after 10th-floor slab casting and on completion of the super structure, and a final 20% plus other charges on offer of possession. All six lines and their triggers are printed on the price list W.E.F. 21-08-2026, set out one by one in the table above.
Turning the ladder into a schedule you can act on
Ask the desk for the 20X5 schedule against your own unit. A percentage ladder is not a schedule. What you plan around is the dated instalment sheet for your configuration, tower and floor, and that is the document we send.
- WhatsApp. Send +91 98114 05300 the configuration you are weighing and we come back with the schedule set against it.
- Call. +91 98114 05300 if you would rather have a consultant take you down the six lines aloud.
- Email. vidit@vidastu.com, if you would rather have the documents on record in an inbox.
The purchase itself is between you and ACE Group, registered in your own name, and every instalment goes to the developer's designated account rather than to us. This desk is paid its brokerage by ACE Group, which is why using this desk adds nothing to what you pay, and it is also why this site is not ACE Group's official website.
Key points
- Five blocks of 20% of the base sale price, with the first block arriving as 10% on booking and 10% within 30 days.
- A fifth of the base sale price is committed on a calendar, before any construction-linked line exists, so the payment instruction and the second due date both belong in writing early.
- Three lines answer to events you can confirm yourself: ground-floor slab casting, 10th-floor slab casting, and completion of the super structure. Ask which tower a demand names, then go and look before you transfer.
- The offer of possession is a letter rather than a site condition, and its printed wording, “20% plus other charges”, opens the bill for heads the price list names without figures.
- Ask for those charge heads itemised in writing at booking stage rather than at possession, so the closing demand reads as a reconciliation.
- The ladder is printed on the price list W.E.F. 21-08-2026 and ACE may revise it. The schedule that binds you is the one recorded in your Agreement for Sale.
Ready to see the 20X5 ladder as dated instalments against your own unit?
Get the schedule on WhatsApp Call +91 98114 05300Frequently asked questions
ACE Arte 20X5 payment plan: how much do I pay and when?
The plan moves in three stages. First, 20% of the base sale price on the calendar: 10% on booking and 10% within 30 days. Then 60% against construction: 20% after slab casting of the ground floor, 20% after slab casting of the 10th floor, and 20% on completion of the super structure. Then the last 20% plus other charges when the offer of possession is issued. Those six lines are as printed on the price list W.E.F. 21-08-2026, and five blocks of 20% is what the name 20X5 refers to. What you plan around, though, is the dated instalment sheet for your own unit, which the desk will send you.
What should I check on site before releasing an ACE Arte instalment?
Three of the six lines describe something you can stand in front of. A ground floor slab has been poured or it has not, a 10th-floor slab has been poured or it has not, and completion of the super structure means the frame has topped out. So when a demand arrives against any of those, ask which tower it refers to and confirm the stage yourself before you transfer. Booking and the 30-day payment have nothing on site behind them, and the offer of possession turns on a letter rather than a site condition, so cover those three with paperwork instead.
How much do I pay in the first 30 days of an ACE Arte booking?
Twenty per cent of the base sale price, made up of 10% on booking and 10% within 30 days, and none of it waits for construction. The first construction-linked line, slab casting of the ground floor, only comes after it. Two things are worth fixing in writing inside that window rather than after it: the account the money must reach, which is set out with the never-pay-an-individual rule on our EOI process page, and the exact date the second 10% falls due against your unit, because no site event will announce it.
What extra costs land with the final ACE Arte payment?
A second bill opens alongside the last 20% of the base sale price, because line six is printed as '20% plus other charges'. The price list names PLC, GST and other charges as extra without printing a rupee figure against any of them, and stamp duty and statutory charges are borne by the buyer. The possession demand is therefore the first document in the sequence where those heads reach you as amounts you have to fund. Ask the desk to itemise them in writing at booking stage, so that letter reads as a reconciliation rather than a first look.
ACE Arte 20X5 plan mein shuru ke 30 din mein kitna paisa dena padta hai?
Shuru ke 30 din mein base sale price ka 20%: booking par 10%, aur 30 din ke andar 10%. Ye dono construction se nahi, calendar se jude hain. Uske baad 20% ground floor ki slab casting par, 20% 10th floor ki slab casting par, 20% super structure complete hone par, aur aakhri 20% plus other charges possession ke offer par, jaise price list W.E.F. 21-08-2026 par chhapa hai. Isliye pehle 30 din mein do cheezein likhit mein le lijiye: paisa kis account mein jaana hai, aur doosri 10% ki exact tareekh. Apne unit ka dated schedule desk se WhatsApp par maang lijiye.
Is the ACE Arte 20X5 payment scheme construction-linked?
Mostly. Of the six lines the price list prints, two fall on calendar dates, 10% on booking and 10% within 30 days of booking, and four fall on construction events: 20% after slab casting of the ground floor, 20% after slab casting of the 10th floor, 20% on completion of the super structure, and 20% plus other charges on the offer of possession. So 20% is due before a slab is cast, and the remaining 80% follows the building.
What is the ACE Arte booking amount?
It has two parts on the price list W.E.F. 21-08-2026. The EOI, refundable in full without any deduction if a unit is not allotted, is ₹10,00,000 for the 1,927 sq.ft* 3 BHK, ₹15,00,000 for the 2,614 sq.ft* 4 BHK, or ₹20,00,000 for the 4,370 sq.ft* 4 BHK + S. Once allotted, the opening line of the 20X5 plan is 10% of the base sale price on booking, into which the EOI adjusts, followed by a further 10% within 30 days.